Westmoreland Conservation District Guidelines for Stormwater & Erosion Control Projects – Contractors’ Workshop 2014

J. Roy Houston Conservation Center

218 Donohoe Road

Greensburg, PA 15601

 

January 17, 2014

7:30 AM – 12:00 PM

 

7:30 AM – Registration and Breakfast

 

8:00 AM – Opening Remarks

Tony Quadro, Assistant District Manager/Technical Programs Director, WCD

John Hardiman, Excavating Contractor

 

8:15 AM – BMPs – What Works and What Doesn’t

Darl Rosenquest, PE, DEP Senior Civil Engineer

 

9:00 AM –  Stormwater Installation Practices

Jim Pillsbury, PE, Hydraulic Engineer, WCD

Chris Droste, Senior Erosion Control Specialist, WCD

 

10:15 AM –  Break

 

10:30 AM – Permits and Process

Kathy Fritz, Technical Programs Administrator

Matt Zambelli, Erosion Control Specialist, WCD

 

10:45 AM –  Utility Stream Crossing Permit and Installation Practices

Chris Droste, Senior Erosion Control Specialist, WCD

 

11:15 AM – Streambank Stabilization Practices and Techniques

Rob Cronauer, Watershed Specialist, WCD

 

11:40 AM –  Critical Stages with Stormwater installations: What is Your Role?

Kathy Hamilton, RLA, Stormwater Technician, WCD

Matt Zambelli, Erosion Control Specialist, WCD

 

12:00 PM – Adjourn